Location:
Beckwourth Ranger District lands; T 26N R 15E Sec
33
|
|
Sponsors:
Plumas Corporation; USDA – Plumas National Forest
|
|
Project Type:
Restoration |
|
Est.
Cost:
$65,000 Amount Funded: $64,000 of
Majority funds May 2005 |
|
Est.
Start Date:
September 2005 Est. End Date: September
2006 |
|
Project Description:
Using
the pond and plug technique the project entails eliminating
1,000 feet of gully on Last Chance Creek, and 800 feet of
gully at the mouth of Jordan Creek. This would involve the
construction of three ponds and four plugs on Last Chance
Creek mainstream, and two ponds and three plugs on Jordan
Creek. The supplemental project would also include 2 1/2
miles of major fence repair around Jordan Flat. The rebuilt
fence would serve to improve grazing management within the
FS allotment by controlling cattle movement in Jordan Flat
and would exclude cattle use in the project area for a
minimum of three years to allow vegetative regrowth to
occur.
|
|
Project Goals/Objectives:
This
project area is now characterized as a xeric meadow with
incised channels. The goal of the project is to restore the
function of the floodplain/channel system. The objective of
the project is to eliminate the gully and return the channel
to the elevation of the floodplain. The project is
justified because its implementation will result in restored
floodplain function, thus attenuating flood flows,
contributing to late summer releases, and improving water
quality and riparian area productivity for wildlife and
meadow productivity for cattle production (which is the
primary land use in this area).
|
|
Project Activities:
June
1, 2005 – September 30, 2005: advertised & awarded
construction and fencing contracts; construction began 9/26;
removed 2 miles of old fence; revegetation of plugs with
native grass seed begun.
October 1, 2005 – December 31, 2005: completed pond and plug
restoration and 2.5 miles of fence construction; completed
revegetation of plugs with native grass seed.
Expenditures through 12/31/05: $63,994.98
2006 Annual Progress Report (Final)
|